Risk management plans (RMP) in post-authorisation phase: questions and answers (2024)

There is only one approved RMP at any time for a medicinal product. Consequently, any time an updated RMP is approved as part of a procedure (e.g. variation, renewal, PSUR), this RMP becomes the approved RMP of the product, and any previous version becomes obsolete. Therefore, MAHs should carefully consider the planning of RMP submission, to make sure that the approved RMP always contains the most up-to-date information on the pharmacovigilance planning and risk minimisation measures.

Given the content-based requirements for RMP submission, it is expected that there will be only few procedures where an RMP update should be included. The MAH should consider whether an RMP is really required with the procedure that is in preparation for submission. Early discussion with the regulators should facilitate the submission, to avoid unnecessary RMP submissions and assessment; parallel procedures warranting RMP updates should be avoided as much as possible.

MAHs are strongly encouraged to streamline RMP amendments and submissions, in co-operation with the EMA for the centrally authorised products, in order to facilitate RMP assessments throughout the product life-cycle.

There are two alternative approaches to the handling of different RMP versions for which the assessment is overlapping, and the MAH should choose the option that facilitates the assessment taking into account anticipated timelines for the finalisation of the procedures.

Whenever separate applications affecting the RMP are submitted in parallel, in order to facilitate the review, it is generally agreed that the MAH initially and whenever appropriate during the procedure submits one joint draft RMP file as a 'working document'. This single RMP document should include all data consequential to the concerned procedures running in parallel . To facilitate the assessment, the proposed RMP changes should be marked (e.g. with different colour code), to differentiate changes specific to each procedure (example: new safety concerns derived from an extension of indication in a new population should be marked differently from the changes in the Pharmacovigilance Plan consequential to (early) termination of a study and initiation of another one as a consequence of the limited safety data gathered in the ended study).

If the parallel applications reach the finalisation stage at the same time, the consolidated RMP version will be adopted by the relevant Committee and will become the approved version of the RMP.

If the applications do not reach the finalisation-stage at the same time, at the time of the first opinion for the parallel procedures, the MAH will need to provide for review and approval a final RMP version including only the agreed changes related to the scope of the variation application for which the CHMP is about to adopt an opinion. The joint RMP 'working document' will continue to be used in the context of the remaining ongoing procedure(s).

Example: A safety variation is triggered whilst an extension of indication procedure is ongoing, both requiring significant changes in the RMP (new safety concern in the new indication; another safety concern and a new imposed PASS in the safety variation). The RMP for the safety variation can be built upon the RMP document submitted with the extension of indication.

Option A: A joint RMP document including changes relevant to both procedures could be submitted with both the responses to the RSI in the extension procedure, and with the initial submission for the safety variation:

  • If both procedures reach the Opinion stage at the same time, than the joint RMP will be adopted and become the approved RMP.
  • If however the extension of indication requires a second RSI, and is most likely to be finalised after the parallel safety variation, the MAH will then have to submit before the opinion for the safety variation an RMP including only the safety concern and the new study related to the safety variation data. This version of the RMP will be checked for consistency and approved with the safety variation opinion. The updated joint RMP 'working document', including the changes consequential to the responses to the second RSI for the extension of indication will continue to be assessed within the extension of indication procedure. This joint RMP will be considered the approved RMP once the extension of indication variation reaches opinion.

A graphical representation for option A is included below:

Risk management plans (RMP) in post-authorisation phase: questions and answers (1)

Option B: Alternatively, it might be more appropriate when parallel procedures will follow very different assessment timetables to opt for an approach similar to the handling of parallel procedures with product information changes; the RMP submitted with each procedure should only include the changes related to that procedure:

  • an updated version of the RMP is submitted as a type II variation to reflect the changes in the safety profile derived from post-marketing reporting. This RMP version should include only the changes related to the RMP update.
  • subsequently or at the same time, another RMP update is submitted as part of a type II variation for the extension of indication. For this application, the RMP version only includes the changes that are consequential to the extension of indication (i.e. not the changes related to the safety variation.

If both procedures conclude at the same time, the MAH is expected to merge the two RMP documents for approval by the Opinion time.

If the RMP update variation is approved before the extension of indication procedure, the RMP submitted will be adopted with the relevant changes and the MAH can submit a consolidated RMP version as part of the MAH's responses to an RSI for the extension of indication. This RMP version includes then the changes approved as part of the recently finalised safety variation (as clean text) as well as the changes related to the extension of indication (with track changes).

The option B can be illustrated as follows:

Risk management plans (RMP) in post-authorisation phase: questions and answers (2)

Regardless of the approach chosen, the MAH should always provide a clear description of the scope(s) of the submission in the cover letter and the changes implemented in the RMP including references to related (previous/parallel) regulatory procedure(s) (see also Question 8 below).

Risk management plans (RMP) in post-authorisation phase: questions and answers (2024)

FAQs

What is the RMP risk management plan pharmacovigilance? ›

Summary of risk management plan (RMP)

RMP aims for the risks of drugs to be evaluated at regular intervals or in response to the progress of post-marketing surveillance and pharmacovigilance activities to minimize the risks of drugs.

What is the post authorization phase? ›

A post-authorisation safety study (PASS) is a study that is carried out after a medicine has been authorised to obtain further information on a medicine's safety, or to measure the effectiveness of risk-management measures.

What is a risk management plan in pharmacovigilance? ›

A risk management plan (RMP) provides information on a medicine's safety profile, describes the activities of the marketing authorisation holder to further characterise the safety profile during post-marketing (pharmacovigilance activities), and explains the measures that are taken in order to prevent or minimise the ...

What is the risk management plan of a drug? ›

A risk management plan (RMP) is a document that describes the current knowledge about the safety and efficacy of a medicinal product. The RMP provides key information on plans for studies and other activities to gain more knowledge about the safety and efficacy of the medicine.

What are the four components of risk management plan RMP? ›

A risk management plan has four core components: identification, evaluation, treatment, and monitoring.

What is the requirements management plan RMP? ›

A requirements management plan is a document that is typically created alongside the primary project plan as a piece of the scope management process. Its primary purpose is to ensure that all stakeholder and business requirements are captured, analyzed, managed, and addressed by the project plan.

What are the three levels of authorization? ›

The first is role-based access control that restricts access based on roles and permissions. Secondly, task-based authorizations are used to specify access rights depending on tasks. Lastly, multi-layered security models define authorizations based on security levels (e.g., public, secret, confidential).

What is the post approval management protocol? ›

A PACMP is a regulatory tool providing predictability and transparency in terms of requirements and studies necessary for the implementation of a strictly CMC (for “Chemistry, Manufacturing & Controls”) change, because the approved protocol of the planned changes constitutes an agreement between the MA holder and the ...

What is post-authorization? ›

A post-authorization, or post-auth, is a type of authorization that confirms the merchant is ready to capture payment of the existing pre-authorized transaction. When the post-auth is processed, the amount is actually debited from the cardholder's account.

What are the four 4 components of a risk management plan? ›

The 4 essential steps of the Risk Management Process are:

Identify the risk. Assess the risk. Treat the risk. Monitor and Report on the risk.

What are the 5 risk management plan? ›

There are five basic steps that are taken to manage risk; these steps are referred to as the risk management process. It begins with identifying risks, goes on to analyze risks, then the risk is prioritized, a solution is implemented, and finally, the risk is monitored.

What is missing information in RMP? ›

“Important missing information”: information which did not acquired at the time of submission of RMP and suggests that it has a limitation in the estimation of the drug safety in the post-marketing setting.

What is the full form of RMP in risk management? ›

RMP coves all aspects of risk management and not just focused on Banking Risk, Financial Risk. We believe that risk management is a holistic concept, not just restricted to banking/Insurance.

What is the RMP for drug safety? ›

An RMP is a detailed description of a risk management system. The RMP contains: the identification or characterisation of the safety profile of the medicine or biological, with emphasis on; important identified risks.

How to do a risk management plan? ›

Learn how to develop a risk management plan to prepare and protect your business.
  1. Decide what matters most.
  2. Consult with stakeholders.
  3. Identify the risks.
  4. Analyse the risks.
  5. Evaluate the risk.
  6. Treat risks to your business.
  7. Commit to reducing risk.
Jan 18, 2024

What is the RPM risk management plan? ›

The RMP rule requires facilities that use extremely hazardous substances to develop a Risk Management Plan which: identifies the potential effects of a chemical accident, identifies steps the facility is taking to prevent an accident, and. spells out emergency response procedures should an accident occur.

What is PMR in pharmacovigilance? ›

The term postmarketing requirement or PMR is used to describe all required postmarketing studies or clinical trials, including those required under FDAAA and those required under subpart H of 21 CFR part 314, subpart E of 21 CFR part 601, the Pediatric Research Equity Act, and the Animal Efficacy Rule.

What is the RMP facility proximity risk management plan? ›

The RMP facility proximity indicator is based on the total count of active facilities with required Risk Management Plans in each census block group within 5 km of the average resident in a block group (or the closest within 10 km), divided by distance, and calculated as the population-weighted average of blocks in ...

What is the role of the RMP? ›

About Royal Military Police

The RMP consists of approximately 2,200 soldiers and civilian staff deployed with other military units throughout the UK and abroad. It is responsible for policing the British Army worldwide.

References

Top Articles
Tour the North Carolina Places That Inspired ‘The Longest Ride’
The amazing setting and backstory of The #LongestRide Movie
Chren, inaugural chair of the Department of Dermatology, to step down
Canvas Rjuhsd
All Obituaries | Sneath Strilchuk Funeral Services | Funeral Home Roblin Dauphin Ste Rose McCreary MB
Social Security Administration Lubbock Reviews
Home Store On Summer
Haunted Mansion Showtimes Near Amc Classic Marion 12
Scriblr Apa
How to cancel subscriptions on your iPhone through the Settings app
Savage X Fenty Wiki
What to see and do in Spokane, Washington
Jack Daniels Pop Tarts
Osu Worday
True Or False Security Is A Team Effort
Busted Newspaper Hart County Ky
Ihop Logopedia
Spicy Korean Gochujang Tofu (Vegan)
Best Builder Hall 5 Base
Lorton Transfer Station
Wolf Of Wallstreet 123 Movies
Ups Customer Center Locations
Amanda Balionis makes announcement as Erica Stoll strides fairways with Rory McIlroy
Bank Of America.aomc
Nissan Rogue Tire Size
SEBO (UK) Ltd on LinkedIn: #sebouk #commercialcleaning #cleaning #floorcleaning #carpetcleaning
Myzynrewards
Garagesalefinder Com
Sweeterthanolives
Cherry Crush Webtoon Summary
Hally Vogel
Winvic First UK Contractor to Use Innovative Technology that Operates Tower Cranes from the Ground
Fedex Express Ship Center
2011 Traverse Belt Diagram
25+ Irresistible PowerXL Air Fryer Recipes for Every Occasion! – ChefsBliss
Parishes Online Bulletins
Syracuse Deadline
Paris 2024: The first Games to achieve full gender parity
Chihuahua Adoption in Las Vegas, NV: Chihuahua Puppies for Sale in Las Vegas, NV - Adoptapet.com
Planet Zoo Obstructed
Cavender's Boot City Lafayette Photos
Sierra Vista Jail Mugshots
Www.craiglist.com San Antonio
Babyboo Fashion vouchers, Babyboo Fashion promo codes, Babyboo Fashion discount codes, coupons, deals, offers
Imagemate Orange County
Mercy Baggot Street Mypay
Solar Smash Unblocked Wtf
Ssndob Cm
Hyundai Elantra - modele, dane, silniki, testy
Trực tiếp bóng đá Hà Nội vs Bình Định VLeague 2024 hôm nay
Craigslist Farm And Garden Atlanta Georgia
18006548818
Latest Posts
Article information

Author: Melvina Ondricka

Last Updated:

Views: 5481

Rating: 4.8 / 5 (48 voted)

Reviews: 95% of readers found this page helpful

Author information

Name: Melvina Ondricka

Birthday: 2000-12-23

Address: Suite 382 139 Shaniqua Locks, Paulaborough, UT 90498

Phone: +636383657021

Job: Dynamic Government Specialist

Hobby: Kite flying, Watching movies, Knitting, Model building, Reading, Wood carving, Paintball

Introduction: My name is Melvina Ondricka, I am a helpful, fancy, friendly, innocent, outstanding, courageous, thoughtful person who loves writing and wants to share my knowledge and understanding with you.